Timeline
January 5 2015
Location Selected
Daikin chooses new mega complex location near Houston, Texas where land is purchased.
January 11, 2015
Ground Breaking
Daikin breaks ground at new location in Waller, Texas.
January 16, 2015
Land Clearing
Clearing of the land has begun on the new campus.
April 16, 2015
Vast Pouring
Ride-on trowels are being used to spread and smooth concrete.
April 19, 2015
Crane Arrival
Construction is progressing at the Daikin Texas Technology Park.
April 25, 2015
Steel Erection
First steel is up, and tilt-wall panels are put into place.
June 20, 2015
Roofing Work
Roofing work on the east end of the Distribution Center.
July 10, 2016
Foundation Slab
Workers install part of a foundation for a large stamping press.
September 12, 2015
Manufacturing
Recent aerial shot of Cypress Creek showing progress on the manufacturing area in the center of the photo.
September 25, 2015
More Steel
Where there’s concrete there’s steel.
October 9, 2015
Tilt Walls Up
Crane sets tilt walls between manufacturing and admin/lab.
October 20, 2015
Admin/Lab Area
Workers place the first concrete of the Admin/Lab area slab.
November 23, 2015
Distribution
Roofing nears completion on the distribution part of the Cypress Creek Campus. The emerging part of the building at upper right will house the assembly area.
November 25, 2015
Looking East
Looking east over the giant Cypress Creek Campus. U.S. 290 at upper right.
December 1, 2015
Drone View
Drone’s eye view of Cypress Creek. The Distribution Center is in the foreground; Manufacturing is being built out at upper right.
December 3, 2015
Tilt Production
Tilt wall production is on display in this recent drone shot at Cypress Creek.
January 28, 2016
First Truck
First truck arrives with the first product.
February 2, 2016
First Staff
As the first trucks arrive, work begins at the new facility.
February 29, 2016
First Product
Changeover has begun with arriving inventory.
March 1, 2016
Operations Begin
This year operations begin at our new $440 million campus – the largest investment Daikin has ever made in its history.
April 1, 2016
Deal of the Year
Our new business campus was recently named manufacturing “Deal of the Year” by the Houston Business Journal.
May 1, 2016
Daikin Texas Technology Park is named
Thanks to Greengrass employees Max Philo and Vijai Venkata for helping us select the facility's name of "Daikin Texas Technology Park" (DTTP).
June 20, 2016
Construction makes great progress, despite weather conditions
We are working diligently on the construction of the offices and labs as an effort to recover lost time from the unexpected high volume of rain experienced in the Houston-area.
June 21, 2016
Roof is completed
Due to favorable weather, we achieved excellent construction progress last week and the entire roof for the facility has now been completed.
June 28, 2016
Office area layout is finalized
The final layout for the office area is currently under review. Toward the end of August, employees from the Houston Logistics Center will be the first group of office personnel to move to the DTTP.
July 1, 2016
Employee Amenities
The DTTP features an onsite health clinic, cafeteria, food pods throughout the facility, walking trails, a dojo learning center, and chillers on the assembly floor.
July 7, 2016
Electrical installations are in progress
The DTTP features an onsite health clinic, cafeteria, food pods throughout the facility, walking trails, a dojo learning center, and chillers on the assembly floor.
July 18, 2016
Deliveries made and progress continues
Construction is progressing well and coordination with the contractor continues as heavy equipment deliveries and installations increased this week. Lab installation started this week and the furniture for the office area was delivered.
July 21, 2016
Crews working onsite while focusing on safety
Several construction crews on the site performing varying tasks from the planting of trees, to hanging lights in labs, to painting in the office areas. Safety is our number one priority as we work together to complete the facility.
July 30, 2016
In the final stages for the Assembly area
Safety continues to be our number one priority as we work to complete the facility. During the past week, our crews started the final stages of work in many areas including the Assembly area and funiture installation in the 2nd Floor area.
May 24, 2017
Official Grand Opening
Daikin Texas Technology Park