HOUSTON (September 12, 2015) – Recent aerial shot of Daikin Texas Technology Park showing progress on the manufacturing area in the center of the photo. The slab at upper left is truck parking for the distribution center and is now complete. A pour is under way on the manufacturing slab-on-grade, center left, next to additional prepped slab forms with their blue liners. With continued dry weather crews are making good progress on concrete placement.